This is how the Butwal-Narayangadh road section expansion work is going on

Falgun 21, 2081

Nabin Paudel

This is how the Butwal-Narayangadh road section expansion work is going on

We use Google Cloud Translation Services. Google requires we provide the following disclaimer relating to use of this service:

This service may contain translations powered by Google. Google disclaims all warranties related to the translations, expressed or implied, including any warranties of accuracy, reliability, and any implied warranties of merchantability, fitness for a particular purpose, and noninfringement.

Narayangadh-Butwal road expansion took 6 years to complete. The road expansion work, which was supposed to be completed in 40 months, could not be completed within the stipulated time. Due to which it is uncomfortable to travel through this road.

Due to potholes, dust, mud and long traffic jams, along with passengers, local residents are also suffering. The contractor company has been delaying the work due to Corona havoc and lack of construction materials. Tree felling order, electric pole shifting and water pipe shifting were also delayed.

This is how the Butwal-Narayangadh road section expansion work is going on

He also appealed to the Prime Minister and concerned agencies to speed up the road construction work from the people's level since the highway was closed. However, the construction company delayed the work citing lack of funds and various reasons. The government had to warn that the contract will be canceled and the construction company will be blacklisted. 

This is how the Butwal-Narayangadh road section expansion work is going on

Now the road expansion work is going on rapidly. The contractor company has accelerated the work of the project with only 5 months left for the third time extension. The contractor company, which did not work even for 4 months after the extension of the deadline, has now accelerated the work on both the eastern and western sections.

This is how the Butwal-Narayangadh road section expansion work is going on

The work of making black sheets, making culverts and cutting mountains in Daunne is now going on in full swing. At present, in the eastern section, Gandakot, Dev Chuli, Kawasoti's Lokaha, Chormara, and Arun Khola sections are being blacked out.

Information officer of the eastern section of the Narayangadh Butwal road extension project, which is currently working at the fastest pace since the construction of the road started six years ago, said Engineer Shiv Khanal. Now the work is being done rapidly.

This is how the Butwal-Narayangadh road section expansion work is going on

The goal of about three percent given in February has been fulfilled,' said Khanal, 'The goal is to complete one-way blacktops in all directions except for the one before the rains.''

About 58 percent of this section of the road, which is 114 kilometers long, has been completed so far. Locals and stakeholders are in a quandary as to whether the work has been accelerated at the last moment for the extension of the deadline and if the extension of the deadline will again slow down like before.

This is how the Butwal-Narayangadh road section expansion work is going on

Now there are more workers on the road than before. The work is also going on fast," said Rajendra Kandel of Sunwal in West Nawalparasi, "Now we have to work at this speed without stopping. '

This is how the Butwal-Narayangadh road section expansion work is going on

Due to not filling the potholes created during road construction and not keeping water on the road regularly, passengers are forced to travel dangerously in dust and potholes. To solve the problem, the people's representatives of East and West Nawalparasi, state and local level met the Prime Minister and drew his attention.

This is how the Butwal-Narayangadh road section expansion work is going on

The construction should have started in March 2075 and completed in July 2079. However, the deadline was extended for the first time till July 11, 2080 due to Corona and construction materials.

After the deadline was extended for the first time, the deadline was extended for the second time until July 8, 2081. But after the work was not completed for the second time, the deadline was extended for the third time. The deadline for

This is how the Butwal-Narayangadh road section expansion work is going on

has been extended until 8th July 2082. The 114 km long road has been divided into two sections, the eastern section and the western section, and the work has been progressed. So far, 65 km one-way and 22 km two-way roads have been black-lettered.

This is how the Butwal-Narayangadh road section expansion work is going on

This project costing 17 billion is advanced with the loan support of Asian Development Bank ADB. 