Nagadhunga-Muglin Road: Due to rain, black sheet work stopped

Ashad 23, 2082

Bimal Khatiwoda

Nagadhunga-Muglin Road: Due to rain, black sheet work stopped

We use Google Cloud Translation Services. Google requires we provide the following disclaimer relating to use of this service:

This service may contain translations powered by Google. Google disclaims all warranties related to the translations, expressed or implied, including any warranties of accuracy, reliability, and any implied warranties of merchantability, fitness for a particular purpose, and noninfringement.

On the Nagadhunga-Muglin road section, which has been divided into three sections and upgraded, the black sheet work has been stopped due to rain. Landslide management is currently being done in all the three sections.

 

If there is a risk of landslides, landslide prevention work is being done according to the road department. The first level of black paper work has been completed in the first section of the three sections under the Nagadhunga-Naubise road section.

The first section of 12.26 km is Nagadhunga-Naubise. In this section, 5.5 km of the second level black sheeting work has also been completed. Keshav Prasad Ojha, Head of Eastern Section of Nagadhunga-Muglin Road Plan, said that although the road will be blacked up to the third level, it is not possible before the monsoon.

The overall physical progress of Nagadhunga-Naubise section is 84 percent. The contract for the upgrading of this section was taken by Jangsu-Sagun JV for 1.3 billion rupees. Chief Keshav Prasad Ojha said that a disabled-friendly Akase bridge is going to be built for pedestrians in this section of mine.

Slope stabilization (landslide control) of a special nature is being done in Jhaple river. Only after its completion will the section be blacked out. "We will not do the black sheeting work before the monsoons, we are working to facilitate the traffic during the rainy season," he said, "We have adjusted the weather in the Sasna section and blacked the sections only when the sun shines." Its distance is 43.54 km. The contract for this section was taken by JICG-Sharma-Lama JV for 5.33 billion 19 million. Its physical progress is 42 percent.

15 km road has been paved in both directions in that section. In this case, the second level of black letter work has not been done. Chief Ojha said that it was not done because it is not durable in the dry season. The office said that after the rain subsides in both these sections, the black letter work will be started from the end of August.

belongs to the third section, Malekhu-Muglin . The progress of this section of 38.86 km is 31 percent. Sharma-JICG has taken the contract for upgrading this section for 4 billion 805 million rupees. According to the agreement signed on 15 December 2079, the work should be completed within December 2082. Kedar Prasad Nepal, head of the west section of the Nagadhunga-Muglin road scheme, which has been black-paved on a four-lane road in the market area, says.

So far only 8.14 km of road has been paved in that section. "It has rained, now black paper will not work," he said. We will keep it in readiness.'

According to him, it has been stopped because black paper is of poor quality during the rainy season. "It is not durable when black paper is used on trees," he said, "Now we will start the black paper work from the end of August when the weather is favorable." The distance from Nagadhunga to Mugling is 94.66 km . 12 thousand vehicles pass through this section daily.

Bimal