Anbukhaireni-Jamune road is in the process of being extended

41.45 km Ambukhaireni-Jamune section construction progress is 87 percent, black sheeting is completed, pavement is being constructed and painting is being done.

Ashad 13, 2082

Bimal Khatiwoda

Anbukhaireni-Jamune road is in the process of being extended

We use Google Cloud Translation Services. Google requires we provide the following disclaimer relating to use of this service:

This service may contain translations powered by Google. Google disclaims all warranties related to the translations, expressed or implied, including any warranties of accuracy, reliability, and any implied warranties of merchantability, fitness for a particular purpose, and noninfringement.

The distance of Ambukhaireni-Pokhara road section under Prithvi Highway is 80.33 km. It has been divided into two sections and the road extension contract has been awarded. The first is Ambukhaireni-Jamune and the second is Jamune-Pokhara.

The contract agreement for the first section, which is 41.45 km distance, was signed on January 8, 2077. The work was started from Baisakh 2, 2078. The contract period taken by China Communications Construction Company was only valid till 2nd Baisakh, 2081 . But after the work could not be completed within that time, the time was extended for the second time until October 2081. But the work was not done. The deadline was extended for the third time until February, the work was not completed. Now the deadline has been extended till June 2082 . The project claims that the work will be completed in the last extended time .

The progress of construction on Ambukhaireni-Jamune section is 87 percent . The contract amount of this section is 6 billion 21 crore 31 lakh rupees.

Now the construction work of this segment has reached its final stage . Overall, the physical progress of Ambukhaireni-Pokhara is 70 percent. But the contract for 8 and a half km of this section has not yet been signed. 

Project Director of Project Directorate (ADB) Chudaraj Dhakal said that the black paper work has been completed in the first section. "The work of two levels of black paper has been completed," he said, "but the landslide management work has not been completed." Although the number of landslides was small at the time of the contract, they were added later, he said, and now they are working on it.

'In the first section, there are 55 small-to-large landslides, of which 8 are large,' Dhakal said, 'Until landslide management, traffic safety, footpaths, painting are completed, the whole work cannot be done, now only that work remains to be done.' The work started from August 13, 2078. According to the initial agreement, the period to be completed is up to August 12, 2081.

Yanhui Kaiyuan Highway and Bridge Construction has taken the contract for this section, so far 55 percent progress. He says that there are three problems of landslides in this section. The expansion of both segments is being facilitated by ADB's concessional loans. The distance of this section is 38.88 km. It is valid till November 2082 . So far, 37 km of one-way tarpaulin has been constructed in this section, in which 26 km of two-way tarpaulin has been constructed, the project said. The contract amount of this section is 7 billion 40 million 46 million rupees.

The contract for Seti and Madi bridges on this road section has been done separately. The contract of Seti Bridge has been taken by Rasuwa Construction. Its contract amount is 1 billion 72 million rupees. So far the construction progress of this section is 46 percent. Its length is 190 meters and two bridges of two lanes have been constructed. The contract for Madi bridge was taken by Anak-JTIEc JV. Its construction progress is 70 percent. This 390 meter long bridge will have four lanes. The contract for both the bridges was signed on July 26, 2079.

It's only valid till August 21, 2082 . It took 9 months to approve the design of both the bridges, even in that the progress in the construction of the Seti bridge is less, it is also a bridge of new technology . That's why it took time to work," said Dhakal, "There is progress on the Madi Bridge. By adding four months time, the work can be done .' He said that it will take some more time as new technology is being worked on at Seti Bridge. In the market area of ​​this road section, the road has been expanded to 6 lanes and elsewhere to 4 lanes . "19 km in Kaski and one and a half km in Dumre and Damauli of Tanahun have been constructed in 6 lanes," he said, "elsewhere it has been expanded to four lanes." But the traffic is high. The power house of the Marsyangdi hydropower project is located in the section where there is a lot of traffic. Again, the project director Dhakal says that this is difficult and complicated section. Where the risk of accidents is also high due to the narrow road, the contract management has not been done on the 8 and a half km road of that section .

Anbukhaireni-Jamune road is in the process of being extended

The Environmental Impact Assessment (EIA) has been approved by the Ministry of Forests and Environment in order to proceed with the contract process for road construction across Muglin. He said that under the new project of ADB that will start in 2026, the work will be started by placing that section.

Bimal