Only 45 percent physical progress in two years, doubts about whether construction will be completed on time
We use Google Cloud Translation Services. Google requires we provide the following disclaimer relating to use of this service:
This service may contain translations powered by Google. Google disclaims all warranties related to the translations, expressed or implied, including any warranties of accuracy, reliability, and any implied warranties of merchantability, fitness for a particular purpose, and noninfringement.
The extension work has stopped in Pulbazar area of Sanga-Dhulikhel road section under construction Arnico highway. Bishnu Khanal, engineer of the Suryavinayak-Dhulikhel, Dhulikhel-Sindhuli-Bardibas road project of the road department, said that since a month ago, the expansion work has been stopped in an area of about 200 meters in Pulbazar area.
According to him, the extension work has been stopped for a month after the locals raised obstruction regarding the issue of the center line in Pulbazar area of the under-construction road section.
He said that preparations are being made to move forward with the expansion work soon by removing obstacles and coordinating between the Napi Department, local people's representatives and locals. According to him, there has been some disruption in Pulbazar area of Banepa. In other places, the work is being done rapidly.
'Now the speed of work has increased in Dhulikhel area,' he said, 'After completing the wall, drain and pavement work in one kilometer area, preparations are being made to pave the road.' Ravindra Shrestha, engineer of construction business Lama Construction Company Limited, informed that along with the obstruction of the local people in the road expansion work, there are also problems such as removing houses and roofs, extending electric poles, removing optical fiber lines and high tension poles. gave
'In Sanga-Dhulikhel road, 3 in Nasikasthan, 2 in Janagal, 1 in Budol and 1 in 28 Kilo, 9 house-towers will have to be removed,' he said, '70 percent of the electricity pole moving work has been completed, now 30 percent is left, there is a high-tension pole in 1 place, it will also have to be moved.' The progress of work up to Bansghari is good . He said that in the areas of 28 Kilo, Budol, Banepa and Pulbazar, there are various problems such as local obstacles, houses and roofs need to be removed.
According to him, the work has been stopped for a month due to the obstruction of the locals in Banepa's Pulbazar . He said that due to these problems, the work will not be completed within the specified time limit. He says that there will be no budget problem for the expansion till this financial year.
After two years of the expansion of the Sanga-Dhulikh road section, only 45 percent physical progress has been made so far in the Suryavinayak-Dhulikhel, Dhulikhel-Sindhuli-Bardibas road project of the road department. The road expansion work was started two years ago to be completed within three years. As only 45 percent of physical progress has been seen in two years, doubts have been raised that the construction will be completed on time.
4 billion 564 million rupees was allocated for the first section of 8 km Sanga-Dhulikhel road section for 6-lane road expansion. Lama Construction Company Pvt Ltd has got the extension contract for that section. According to the project, the contract for the second section of the 7.5 km Suryavinayak-Sanga road section in the second section under the expansion plan is worth 3.888 billion 93 lakhs.