The distance from Ambukhaireni to Pokhara under Prithvi Highway is 80.33 km. Whose overall physical progress is 67 percent. The contract for 9 km of Mugling-Ambukhaireni (East) section has not yet been signed. The progress of Ambukhaireni-Jamune section is 82 percent and the progress of Jamune-Pokhara (West) section is 46 percent.
Ambukhaireni-Jamune's initial deadline was till 081 Baisakh . The deadline was extended for the second time until October, but the work was not completed. The deadline was extended for the third time until February. The deadline has been extended for the fourth time till June 16, 2082. The distance of the eastern section is 41.45 km and the distance of the western section is 38.88 km.
The project director of the Directorate of Projects (ADB) Chudaraj Dhakal said that 38 km of road black paper work has been done in the eastern section and the remaining black paper work will be completed within a month. In that section, 20 km of black sheet work has been completed on the second level in both directions. In this section, the service lane is only one and a half km.
"In the western section, 28 km has been paved, of which 14 km has been one-way paved," he said, "two km out of the contract has not been demolished, we will make the road section smooth one-way by June 16, 2082." are .
Since Seti and Madi Bridge contracts have been done separately. The contract of Seti Bridge has been taken by Rasuwa Construction. Its contract amount is 1 billion 72 million rupees. So far the construction progress is 46 percent. Its length is 190 meters and two bridges of two lanes have been constructed. The contract for Madi bridge was taken by Anak-JTIEc JV. Its construction progress is 67 percent. This 390 meter long bridge will have four lanes. The contract for both bridges was signed on July 26, 2079 and its term is up to August 21, 2018. Bridges and roads have been upgraded with concessional loans from the Asian Development Bank (ADB).
While work is being done on the Ambukhaireni-Pokhara section, there is still no chance of awarding a contract for the Muglin-Abukhareni road upgrade. It is said that the project will take two and a half years to build if the contract is awarded. The road from Muglin to Ambukhareni is narrow. But the traffic is high.
The power house of the Marsyangdi hydropower project is located in the section where there is a lot of traffic. Again, director Dhakal said that this is difficult and complicated section. Where the risk of accidents is also high due to the narrow road, the contract management has not been done on the 8 and a half km road of that section . According to the project, the Environmental Impact Assessment (EIA) has been approved by the Ministry of Forests and Environment in order to proceed with the contract process for road construction across Muglin.
A two-lane road will be constructed along and across the said road section. It has been designed to build one concrete bridge each at Trishuli under Muglin Bazar and at the Power House of Marsyangdi Hydropower Project. He said that the bridge will be built about 400 meters from Marsyangdi Power House. After that 4 lane road will be constructed . It is estimated that the construction of Muglin-Ambukhaireni section will cost 4 billion rupees. He said that he is also talking with ADB regarding its construction.
Pathlaiya-Hetaunda-Narayangadh road is being designed under ADB to be upgraded and Muglin-Ambukhaireni section will be contracted along with this section, Project Director Dhakal said.