The blockage of Kamalbazar-Dailekh 33 KV transmission line has been removed

Magh 15, 2081

Tularam Pandey

The blockage of Kamalbazar-Dailekh 33 KV transmission line has been removed

We use Google Cloud Translation Services. Google requires we provide the following disclaimer relating to use of this service:

This service may contain translations powered by Google. Google disclaims all warranties related to the translations, expressed or implied, including any warranties of accuracy, reliability, and any implied warranties of merchantability, fitness for a particular purpose, and noninfringement.

The electricity extension work, which was blocked by the residents of Achham side demanding to be able to turn on electricity in the village, has been resumed from Monday. According to the demand of the locals of Achham, after the electricity poles, wires and transformers reached the village, the locals allowed the work of pulling the line to resume.

 

Residents of Panchdeval Vinayak Municipality-3 Belkhet Sayan Village and Ward-4 Todkesal of Achham obstructed the extension of the 33 KV line from Achham Kamalbazar-Dailekh Saigaon saying that they will not allow the extension of the power line until the electricity is turned on in their village. 

Nepal Electricity Authority Sudurpaschim Province Office Attaria provided poles, wires and transformers needed to electrify the settlements of Belkhet and Todkesal and allowed the line extension work to go ahead, said Chhatra Bahadur Bista, leader of Todkesal.

'There was no hearing until the work was stopped,' he said. He told me that he was allowed to work because he had cleared half of the goods. "It is not our desire to stop laying the power line to Karnali. Many times, after not hearing from Achham, only hearing was heard when the work was stopped,' he said. 

Jaiprasad Pandey, an employee of Kalikot Electricity Distribution Center, said that since some poles and wires have arrived in the village, the work has been resumed as per the consent of the locals to resume the work. According to him, after clearing the line from Achham's Kamal Bazar, it has reached Belkhet village. Electricity will reach the villages of Kalikot, Jumla and Mugu in Karnali after the completion of the 33 KV line extension within a week.

In the discussion held in Belkhet of Achham, Kalikot Electricity Distribution Center Chief Harendra Rai Yadav, employee Pandey, Dailekh Electricity Chief Naresh Dutt Rawal, employee Padam Thagunna, Bista who is also a former teacher on behalf of the locals, Dammar Bahadur Baduwal, Sher Bahadur Bista signed the necessary poles, wires and It is mentioned to provide a transformer . 

The joint meeting procured 50 pcs of 11 meter steel tubular pole, 40 pcs of 8 meter steel tubular pole, 46/46 pcs of 1200 and 300 mm panels, 138 pcs of 11 KV insulators, 24 sets of dis insulators, 120 kg of stay wire, 50 mm cables. It was also decided to provide goods including 8 kilo meters and 1 transformer. Locals obstructed the extension of 33 KV transmission line of 9 km distance from Kamalbazar in Achham to Saykhola in Dailekh. They demanded that electricity should be given to them while laying a line by burying an electric pole from their farm. 146 households in ward 3 Belkhet Sayan and ward 4 Todkesal were in the dark.

9 km long 33 KV transmission line from Kamalbazar in Achham to Saikhola in Dailekh through Kalikot Power Distribution Center last June, stating that 19,000 electrified households in Kalikot, Jumla and Mugu did not get electricity due to the voltage of the national transmission line reaching Kalikot, Jumla and Mugu through Kohalpur, Surkhet, Dailekh. 1 crore 88 lakhs tendered to be able to work in 6 months of extension The work had started . Out of the 9 km from Kamalbazar in Dailekh to Saikhola in Dailekh, the work was interrupted when only about 100 meters of wire was left to be pulled from across the Karnali river to Wari.