The physical progress of the 140 megawatt capacity Tanahun hydropower project under construction at Jhaputar in Risching rural municipality-1 Kahunshivpur of the district has reached only 63 percent. Divided into three packages, the overall financial progress of the project under construction is 58 percent.
Shyamji Bhandari, head of the project, said that grouting is being done in the lower level area of the main dam under package-1. According to him, a 140-meter high main dam will be constructed on the Seti River, which flows through the border of Risching-1 and Beas Municipality-5.
'Crusher and damping plant have been installed and kept ready', he said, 'We are preparing to start construction of the main dam soon.' Song Da Corporation, Vietnam-Kalika Construction Pvt. He said that the percentage is .
Similarly, under Package-2, the concrete lining of the 1493-meter long tunnel starting from the intake (intake) of the reservoir and ending with the penstock pipe is being 'break through' and concrete lining said . "The water from the main tunnel will be produced through a 213-meter long penstock pipe in the underground power house," he said, "for this, the penstock pipe connection has reached the final stage." , construction work including connection and operation is being done by Sino Hydro Corporation China . The construction of the civil structure of the power house is in the final stage. According to the project, construction of swissyard, installation of equipment in the power house, etc. are underway. The physical progress of this package is about 62 percent . Under
package-3, KEC International Limited India has undertaken the construction of a 220 kVA double circuit transmission line from Damauli to Bharatpur in Chitwan. According to the project, out of the 94 towers in the 34.7 km transmission line, the foundation of 78 towers has been laid and 69 towers have been erected. The progress of this package is 74 percent.
The overall construction is set to be completed by June 2083 (May 2026). A team consisting of Director of ADB's Nepal Housing Mission, Arnold Kushwa, and Kulman Ghising, Executive Director of the Authority and Chairman of the Board of Directors of Tanahun Hydropower Limited, conducted on-site monitoring of the project on Monday and instructed to complete the construction on time. Tanahun rural electrification and distribution system strengthening project has been completed through the project management directorate of Nepal Authority to electrify Tanahun district under the social development program of
project. Under this, two substations of 33/11 kVA have been built and put into operation in Ghiring Rural Municipality-4 and Bandipur Rural Municipality-6 for local electricity supply. A 33 KVA line has been constructed to deliver electricity to the said substations. Distribution transformers of different capacities have been installed and 11 KVA lines have been constructed in various places to make the electricity supply of Tanahun district sufficient, reliable and of good quality. Under the
community development program, 63 projects including education, health, drinking water, roads, river embankment construction etc. have been completed in the project affected areas. 10 projects are running . Various skill-based trainings are being conducted for the livelihood and income generation of project affected people.
The total cost of the company's capital structure and financial management project (including transmission lines, rural electrification and interest during the construction period) is 150 million US dollars by ADB, 184 million by Japan International Cooperation Agency (JICA), and 184 million by European Investment Financial management has been done so that the bank will bear 85 million dollars and the Government of Nepal/Nepal Electricity Authority will bear 86 million dollars .
Company has advanced the development process of 126 MW Lower Seti Hydropower Project in the lower coastal area by using the flow and Madi River water obtained from the project.