Kanti Lokpath will be operational from Sunday morning

Bailbridge connection at Wagmati Bridge till Saturday night

Jestha 24, 2082

Pratap Bista

Kanti Lokpath will be operational from Sunday morning

We use Google Cloud Translation Services. Google requires we provide the following disclaimer relating to use of this service:

This service may contain translations powered by Google. Google disclaims all warranties related to the translations, expressed or implied, including any warranties of accuracy, reliability, and any implied warranties of merchantability, fitness for a particular purpose, and noninfringement.

Kanti Lokpath road connecting Hetauda-Kathmandu will be operational from Sunday. Kanti Lokpath will be put into operation from Sunday as the belay bridge will be installed on the bridge of Wagmati river towards Makwanpur under Kanti Lokpath by Saturday night.

"Even if we work till 12 midnight on Saturday, we will bring the Kanti Lokpath into operation from Sunday morning," said Ratnalakshmi Bajracharya, head of the Kanti Lokpath road project, "Workers and technicians have been working 24 hours a day to install the belay bridge since May 21."

About 50 workers and technicians with three excavators have been deployed for the past four days to install the belay bridge towards Makwanpur of Wagmati bridge. Project engineer Sajan Neupane said that the work of installing gavin for the protection of Belybridge is also underway.

On October 11th and 12th, after the flood in the Wagmati River washed away one of the spans of the Wagmati Bridge towards Makwanpur, the Kanti Lokpath was made operational by making an access road of mud and sand. After the flood in Wagmati river washed away the access road before the start of rainy season, the belay bridge is going to be installed at that place.

The Kanti Lokpath road project has closed the Lokpath for four days from 21st June i.e. Wednesday to 24th i.e. Saturday and installed the Beilibridge. Bhimfedi Rural Municipality-8 of Makwanpur and Wagmati Rural Municipality-2 of Lalitpur, a span of the Wagmati river bridge towards Makwanpur was swept away by the flood on October 11th and 12th.

Kanti Lokpath road project has installed a 24.4 meter long and 5 meter wide belay bridge at that location. According to the project, the construction company has been given a contract for about one and a half million to carry out protection works including Belybridge connection, Gavin.

When the Kanti Lokpath was closed for four days, vehicles running Hetauda-Kathmandu and Kathmandu-Hetauda have been using Kulekhani-Kalanki-Humane or Kulekhani-Sisneri-Pharping road. 

Pratap