Under the Narayanghat-Butwal section of the East-West Highway, which is being expanded to four lanes, 47 km of the 65-km eastern section has been paved.
According to the Narayanghat Butwal Road Project (East Section) Office, so far this road has 58.7 percent material progress has been made. After completing 16 km of black road towards Gandakot, black road is being laid in Devchuli municipality. 22 small bridges have been constructed in this section.
The construction of the link road on the completed bridge Shiv Khanal, information officer of the said office, said that it will take time to operate the means of transport from the bridge because there is no such thing.
Binayi Khola bridge is being worked on at a fast pace with the goal of completing it before the next monsoon. A few weeks ago, after the bridge was damaged due to an overloaded truck, the vehicles were diverted.
Rakesh Jha, co-manager of China State Construction Engineering, the construction company that got the contract for road expansion, said that road expansion is continuing in 42 places.
'We have focused manpower on bridge construction along with road expansion', he said, 'We are working by mobilizing more than 650 workers including culvert, sub base, base, filling, drainage, gabion, along with road paving and bridge construction.' The goal is to be done by Dumkibas by the end of the month. "The cutting of the hill in the eastern section has been completed," he said