The municipal basic hospital building of Doti, which was laid three years ago, has fallen into disrepair. The hospital building has been left stranded after the construction companies have made various excuses for collecting lakhs of rupees.

Municipalities have signed an agreement for the construction of 7 hospital buildings with an investment of 685 million rupees in Doti. The contractors have already realized the advance amount of Rs. Durga Ojha, president of Jorayal Rural Municipality, said that the contractor companies have been ignoring the frequent requests of the municipalities. He complains that the progress of the work has not progressed even though some municipal heads have warned that the contractor will be blacklisted. 

Out of 9 of Doti, 7 local levels namely KI Singh, Zorayal, Sayal, Badikedar, Bogtan Foodsil, East Chowki Rural Municipality and Shikhar Municipality laid the foundation stone for the construction of basic hospital building in November 2077. Apart from East Chowki, work is still incomplete in 6 municipalities. In Adarsh ​​and Dipayal Silagadi Municipalities, the construction work has been re-contracted from the current financial year and the work has progressed. 

35% of Badikedar, 48% of KI Singh, 20% of Bogtan Foodseal, 5% of Sayal, 11% of Zorayal, 80% of Shikhar have been completed. "Despite repeatedly warning the contractor in writing, there was no progress in the work," Sayal Rural Municipality Chairman Dharmaraj Joshi said, "We have already initiated the action process according to the law." They have been arguing that they could not move forward. There is no field anywhere according to the contract, it seems different that one should be built somewhere in Stimate,' said Ghanshyam Pathak, president of construction business association Doti, 'due to the weakness of the municipality, the work has not progressed due to the increased financial burden on the construction business.' 

An agreement was signed with Dhulikhel LB & AB Jayashree Balaji JV on October 4, 2078 for the construction of a 10-bed basic hospital building in Badikedar Rural Municipality. According to the agreement, the construction work of the building was supposed to be completed on 29 November 2079, but the building is still incomplete. Although the term of the contract agreement has been extended till the middle of December 2080, the work has been done only 35 percent . Sandeep Neupane, the chief administrative officer of the village informed that the contract was signed for Rs.

The 15-bed basic hospital building to be built in Bogtan Fudsil Rural Municipality-2 is also stalled. An agreement was signed between the rural municipality and CM-Prasanna JV for the construction of the building on 18 June 2078.

Chief Administrative Officer Bharat Bahadur Chand said that only 20 percent of the building that was supposed to be completed on 29 June 2079 has been completed. Due to the agreement of 1482 million 10000 rupees including VAT, the builder has so far taken payment of 29 million peski and 6850 thousand 925 rupees in running bills. The term of the contract has been extended until June 2081, according to the rural municipality.

The condition of the 10-bed hospital building to be built in KI Singh Rural Municipality is also the same. Surat Bahadur Pariyar, the chief administrative officer of the rural municipality, informed that the construction of the hospital, which was supposed to be completed on 23 October 2079, is only 48 percent complete.

An agreement was signed between the rural municipality and KS-Tedi-Manilek JV on 23rd June 2078 to complete the construction at a cost of Rs 8 crore 15 lakh 78 thousand including VAT. The builders have taken payment of 1 crore 89 lakh 81 thousand rupees so far. It is said that the building should be completed on June 20, 2081 with an extension. Village Chairman Lokendra Bahadur Shahi said that the construction company, which has not been in contact for a long time, came and resumed work only a week ago.

The plight of the building said to be constructed in Sayal Rural Municipality is also the same. The municipality has informed that only five percent of the building, which should be completed on July 30, 2081, has been completed so far. TDR Construction Pvt Ltd got the contract for the construction of the 10-bed building which is being constructed near the village health post. The rural municipality has informed that the contract was signed on 30th July 2078 to construct the building for 84.46 million 34 thousand including VAT.

The 15-bed hospital building of Zorayal Rural Municipality, which should be completed and handed over by the end of June 2080, has only been completed by 11%. According to the information given by Ganesh Dutt Bhatta, the chief administrative officer of the rural municipality, an agreement was signed with Varah Developers Pvt. 11 crore 21 lakh 58 thousand rupees including VAT, so far 1 crore 96 lakh rupees have been paid to the builders.

Shikhar Municipality's 15-bed hospital building is also incomplete. An agreement was signed between the municipality and the construction company KS Construction Pvt.

Municipal information officer Kalpana Thakulla informed that 80 percent of the building, which was contracted for Rs 100,300,700, has been completed. She also said that the term of the contract is up to Chait 30. So far, the builders have collected Rs 6 crore 61 lakh 11 thousand.