The cold store, which was supposed to be built in 17 months, is stalled even after 6 years

चैत्र १४, २०८१

विद्यानन्द राम

The cold store, which was supposed to be built in 17 months, is stalled even after 6 years

The construction of the Cold Store (Cold Store) which was started at Deuri Bharuva, Rajviraj Municipality-15 of Saptari, said to be completed in 17 months, has not been completed even after 6 years. On December 16, 2075, Ashish/Om Sairam JV of Lalitpur signed a contract for a cold store to be built for a total of Rs.

The construction of cold storage was started with a partnership of 60 percent of the federal government and 20/20 percent of the state government and the district cooperative association.

Ramesh Kumar Gupta, manager of District Cooperative Union Saptari, said that the construction company stopped the work as the payment was not made according to the progress of the work. He explained the background of the fact that despite the extension of one year on 18th June 2078, the amount could not be paid by the federal government, he said, "According to the last letter sent by the ministry to the municipality on January 6, 2018, it is mentioned that additional budget cannot be given to the cold store due to lack of resources." 76 thousand 823 rupees is still to be paid by the construction company. He said that so far 1 crore 8 lakh 54 thousand 367 rupees from the cooperative, 1 crore 4 lakh 15 thousand 118 rupees from the state government and 6 crore 36 lakh 34 thousand 400 rupees from the federal government have been spent on the work including DPR.

विद्यानन्द राम विद्यानन्द राम कान्तिपुरका सप्तरी संवाददाता हुन् । उनी समसामयिक बिषयमा रिपाेर्टिङ गर्छन् ।

Link copied successfully