The work of opening the Belybridge of the Hewa River on the Mechi Highway, which has been broken, has reached its final stage.In the evening of May 31st, the under-construction Beilibridge was broken during the installation process.
When the bridge collapsed, 3 people lost their lives and 3 people were injured.
The concrete bridge of the Hewa river in the Panchthar section of the Mechi highway was swept away by the flood on 2nd June 2080 for the first time.
After that, the belay bridge installed here was again swept away by the flood on October 12th, and the belay bridge that was started for the third time broke when the work was completed, and this area of the Mechi highway is without a bridge. When it doesn't rain, vehicles can cross through the diversion, but when it rains, the river rises and covers the diversion, so traveling in this area is difficult.
road The work of connecting and opening this bridge is being done by Road Division Ilam. After opening the
, the road division of Ilam has a plan to connect the beli bridge again at this place.
According to Pawan Bhattarai, Head of Division Roads Ilam, Belibridge is planned to be opened by Monday.