When will a new city be built in Rakam?

5 percent work in 13 years

kartik 16, 2081

Jyoti Katuwal

When will a new city be built in Rakam?

We use Google Cloud Translation Services. Google requires we provide the following disclaimer relating to use of this service:

This service may contain translations powered by Google. Google disclaims all warranties related to the translations, expressed or implied, including any warranties of accuracy, reliability, and any implied warranties of merchantability, fitness for a particular purpose, and noninfringement.

The work of the new city project in Rakam Karnali in Athavis municipality is at a standstill. Rakam Karnali of Dailekh was also selected as the government planned to build new and modern organized cities in 10 different locations across the country from the financial year 2067/68. But even after 13 years, the work of city administration is still in a state of stagnation.

By 077/078, the government has already selected 54 cities to create new and modern organized cities in an attractive and attractive manner.

Government work with the plan to complete the construction work within 5 years has not been done in a significant amount even after 13 years. There are only works like making general drains and putting solar. The interest of when the new city will be built is years old. Even after 13 years of starting the work, it is not seen to be organized and modern city.  The

project said that since there is no public land, it took time to manage the land. Tek Bahadur Majhi, Ward Chairman of Ward-4, said that there has been no visible work since the establishment of the office. It was said that the first employee does not agree to stay. The employees sat in Surkhet and took salary from Dailekh,' he said, 'Government has not been able to prioritize the project, what can be expected of other work?' ; The

project has so far done water supply, waste management, health building, solar, security, amusement park roads and other works at the workplace. The project chief Praveshraj Lamichhane said that the work was delayed due to lack of coordination and clear procedures related to land pulling by the department. "Because there is not enough public land, land management has taken time," he said. Along with the land, the local government also did not show interest in the work. According to him, it is not just about building the project, there are also many challenges here.

The project has a big challenge to protect the settlements on the banks of the Karnali river from floods. Lamichhane, the head of the project, said that the work was not done according to the agreement and there was a delay due to insufficient budget. "Earlier, a small budget was used, but the work could not be done, but even now, the size of the budget is decreasing. " 

Local Maya Shahi said that the project only built her building as visible work. "Since 13 years, the office has not been able to advance 5 percent of the work," she said, "The work of opening the office has only been to pay salaries to the employees." According to the project office, in 2081/82, there is a plan to manage drains and open areas in the land polling area . As the parcel of land has been consolidated, the permanent portion will be distributed soon.  Although the target was to spend 20 billion upon completion of the

project, only 32 million has been spent in 13 years . The project has 137 ropani of land in 56 lots of the place where the new city is being built. The Office of New City Development Project will give 70 percent of the land to the local people and the remaining 21.17 percent will be constructed as roads and drains, 5 percent will be open areas, and 3.83 percent will be sold by the Planning, Urban Development and Land Development Committee. Kalpana Thapa, Deputy Chief of Athavis Municipality, said that the project has affected the work due to lack of budget. ``If we work according to the allocated budget, only 5 percent of the work will be done in 13 years ?'' She said, ``many times the municipality urged us to do the work at a fast pace, but it was not listened to . Because of the program of the union, the local level does not accept what they say.'

Jyoti