19 houses under the road jurisdiction of Madhyapahari Lokmarg have been demolished. The upgradation work has been started by demolishing the houses connected with the road in Luitelbhanjyang, Bahrapirke and other areas under the Masanethanti-Thantipokhari section. Homeowners demolished their houses for road construction.
Palungtar Municipality-4 Luitel Bhanjyangka 10, Bahrpirkeka 6, ward no. 2 Putlikhetka 2 and ward no. 1 house in Dhurpulekhar was demolished, said engineer Govind Shrestha of Palungtar, Madhyapahari Highway Planning Office. In the very old Luitel Bhanjyang, only 10 houses were within the jurisdiction of the road.
The traditional houses made of stone and mud in Luitel have been demolished and road upgrading has been started after the road is in the middle of the market area . "Luitel Bhanjyang's market is very old, we used to walk this way to Kathmandu-Pokhara," said Uma Shrestha, a local, "The road came in 2052, then we stopped walking, now we have demolished the house to widen the road." "We are ready to demolish the house we have been living in for years to widen the road," she said, "It has been a long time since the house was demolished, the mud of the destroyed place is still there, so far no one has come to remove it, the road to demolish the house is not going to be paved, it is starting to get worse." "After it was destroyed, it would have been fine if the soil had been layered, there is a small part left behind, and a roof could have been built there," she said.
She said that she felt very embarrassed when she had to destroy her own house. She has removed the wood of the old house and kept it safely. According to Engineer Shrestha of Madhyapahari Highway Planning Office, Palungtar, the house which is within 6/6 meters to the right of the road has been demolished and upgraded.
He said that in the case of houses built with earthquake relief funds, the district administration office has decided to provide the costs of demolition. "We have decided to pay 20,000 rupees for the raw house, 30,000 rupees if it is made of mud and 45,000 rupees if there is some plaster work with mud and mud," he said.
He also said that the process is underway to provide the amount. Shrestha informed that the decision is yet to be made in the case of the five houses that did not receive relief from the earthquake.
Out of the 62 km under the Madhyapahari Highway in Gorkha, two sections of the work have not been completed due to the delay of the contractor . Shrestha said that currently 54 percent financial and 56 percent physical progress of the Masane Thati-Palungtar section, which is due by this April, has been completed. Himjung Pacific JV has got the responsibility of about 16 km of blacktop of that section.
Shrestha said that the work has intensified lately. "At least 10 kilometers of roads will be paved in this section this year," he said. Structure and drain work is being done for the blackboard . He said that the black paper will start from next week as the work of keeping the shelter is also going on.
The contractor company MP SCF ACC JV signed a contract for 16 km of black paper from Okhle to Nivel on 10th January 2072 . In a period of 9 years, the term of the contractor has been extended for the sixth time .
was last added and the deadline has expired on the 5th of last year . Shrestha said that the progress of the section is 89 percent. He said that the work has intensified in that section now. "8 kilometers were paved last year, the target is to be completed this year, even if not, another 4/5 kilometers will be paved, the work is also underway," he said. Madhyapahari road will be widened by seven meters.
"Soldier" dead meter and drain also construction he said. "Despite the expiry of the contract period of both sections, the work is still going on, the process of extending the term is also going on," he said. The work of three sections of Waki in Gorkha under Madhyapahari has been completed . Out of 62 km in Gorkha region of Madhyapahari, 24 km road is being paved, said the office. This year, the target is to make 18 km of black paper .