Beileybridge ready in Kulekhani Simkhola, vehicles started moving

Traffic was diverted from the river until the Bely Bridge was operational.

Bhadra 6, 2082

Pratap Bista

Beileybridge ready in Kulekhani Simkhola, vehicles started moving

We use Google Cloud Translation Services. Google requires we provide the following disclaimer relating to use of this service:

This service may contain translations powered by Google. Google disclaims all warranties related to the translations, expressed or implied, including any warranties of accuracy, reliability, and any implied warranties of merchantability, fitness for a particular purpose, and noninfringement.

Small vehicles have started to pass through the Beilibridge constructed in the Simkhola under the Kulekhani hydropower project dam.

Naveen Singh, Head of Transport Infrastructure Directorate, Hetaunda, said that vehicles weighing up to 6 tons have been allowed to pass through the bridge. According to him, heavy vehicles have been banned.

After completing all the work in 40 days, the vehicle has been started to operate. On the Bhainse-Bhimphedi road section, 2 balibridges which were not in use were removed and installed in Simkhola. 30 technicians and workers were employed for this.

Beilibridge was built because the right and left side of the bridge, i.e. the access road, was washed away. Gaurav Engineers Pvt.

Beileybridge ready in Kulekhani Simkhola, vehicles started moving

After the Kulekhani was filled with heavy rain on October 11 and 12, when the gate was opened to prevent 'overflow', the road along with the Simkhola bridge in the lower part of the Kulekhani Dam located in Indrasarovar Rural Municipality-2 was damaged. Traffic was diverted from the river until Ballybridge operation came. 

Pratap