The lining work of the main tunnel of the Siddhartha tunnel at Dobhan, Tinau rural municipality-3 of Palpa under the Siddharth highway has been completed. Out of 1126 meters of tunnels, the tunnel is 1089 meters long.
Krishnaraj Adhikari, Head of Siddhababa Tunnel Project Office informed that the structural coating (lining) work to be done on the inner wall of the inner tunnel of the main tunnel has been completed. He said that the wall inside the
tunnel is covered with concrete, shotcrete, blocks or other materials. "It gives stability to the tunnel, reduces the possibility of rock falls and stops water leakage," he said. The chief official said that after lining, the tunnel will be safe, strong and usable.
The ground slope (invert) work has already been completed. The Siddhababa Tunnel Project Office said that the invert work has also been completed for 1089 meters. Along with this, the work of the North and South portals has also progressed. The chief officer said that 19 meters to the north and 18 meters to the south should be done. "After the completion of the invert and lining work, the work on the north and south portals has progressed," he said. He said that the foundation has been prepared on the north side and work is also underway on the south side. If there are no obstacles or other problems in between, the project office said that the vehicles will be able to pass through the main tunnel in the next 7 months. Lining and invert work has also progressed rapidly in the three bypasses here. Bypass one is 151 meters long, bypass two is 161 meters and bypass three is 130 meters long.
Invert work on Bypass 1 has been done for 145 meters. The lining work has also been done for 129.7 meters. In Bypass 2, the work of invert has been done for 157.8 meters and the work of lining has been done for 65.4 meters. 125 meters of invert work on Bypass 3 has been completed. According to the project office, the work of lining has been done for 109.8 meters.
The project is planned to speed up the work of the tunnel main tunnel. The chief project officer said that the internal work has been accelerated because the plan is to send vehicles from inside to outside and work on the current road. He said that because there is a river outside and there is a river in the lower part, it will be a problem to work.
The road safety work has progressed by using slope stabilization and rock barrier method in the risky area of Siddhababa area. He said that stones will be removed in the area of possible accident and strong wire netting will also be laid on the upper part of the mountain. From which the slope protection work has started in the landslide prone area. There will be a rock barrier on the hills here. On the south side of the tunnel area, out of 2,300, 1,495 meters of slope protection work has been completed.
495 out of 1100 works have been completed in the north. MROne Mountain Side is only 481 out of 9620. Project Chief Officer said that out of 7440 meters of MR2 mountain site, 1414 meters have been worked. The work of MR One Riverside 1360 and MR Two Riverside 500 meters has not progressed. Under the project, the Chinese company China State Construction Engineering Corporation, a construction company, has completed the work of 9 culverts and is working on the construction of drains. As of August 30, the physical progress of the tunnel has been completed at 61.06 percent. The project office said that the financial progress is 51.01 percent. As part of the
project package, the Chidiakhola-Siddhababa temple and the road from North Mohoda to Dobhan in the tunnel will also be used to reduce risk using modern technology, according to the project. The strong wire mesh is expected to be able to hold stones up to 5,000 kg.
The arrangement of falling of large stones will be arranged by reducing the speed. According to the project, rock barrier and slope protection work will be done in Chidiakhola-Siddhababa temple and Dobhan section after the rains. The Chinese company China State Construction Engineering Corporation has signed a contract to build a tunnel at a cost of 7.34 billion 21 lakh rupees including value added tax. This project was agreed to be completed within 5 years in February 2078. According to the terms of the contract, the construction must be completed within 5 years from the start of construction in the first phase, i.e. on 8th Chait 2083.
After the construction of the tunnel, the citizens of Palpa, Rupandehi, Gulmi, Arghakhanchi, Rupandehi, Syangja, Pokhara, Baglung, Mustang and other areas of Lumbini and Gandaki provinces will be able to travel safely.