The under-construction bridge at Pankhukhola under Madhyapahari Lokmarg is stuck. Diktel Rupakot between Mazhuwagadhi Municipality-8 Bualung and 9 Nirmalidada has been stuck after the construction company did not take the contract and work.
Siruva Construction Pvt Ltd signed an agreement on 7th of October 2072 to be completed by 6th of October 2073 at a cost of around 20 million rupees.
The deadline has been extended time and time again till 30th October 2077 Hark Pradhan, information officer of the Madhyapahari Highway Plan said. According to him, only 39.84 percent progress has been seen so far in terms of physical and financial aspects. The last time the deadline was extended until 30th of October 2077, Pradhan said, "By the end of this period, only 39.84 percent is seen in terms of physical and financial performance." . Pradhan told that the construction company was blacklisted after breaking the contract after not working.
Pradhan said that a file has been sent to the Ministry of Finance to ensure resources to complete the construction of the bridge. Pradhan said that the tender will be re-tendered once the source is ensured. "A file has been sent to the Ministry of Finance to ensure the resources for the construction of the bridge," Pradhan said. Kathayat also said that if the work is not started on time, they will go on strike. "The condition of the road bridge like Madhyapahari is like this," said Kathayat, "the attention of the relevant bodies should be taken soon, otherwise we will protest."