The committee, which has been drawing water from the unfinished lift project to avert the water crisis, is deprived of the facility of tariff exemption even though it is spending 60 lakhs annually on electricity tariffs.
We use Google Cloud Translation Services. Google requires we provide the following disclaimer relating to use of this service:
This service may contain translations powered by Google. Google disclaims all warranties related to the translations, expressed or implied, including any warranties of accuracy, reliability, and any implied warranties of merchantability, fitness for a particular purpose, and noninfringement.
Baglung Nagar Water Supply and Consumers Committee has been paying electricity tariff of five lakhs per month while distributing water to common consumers through elevators. The committee, which has been drawing water from the unfinished lift project to avert the water crisis, has been deprived of the facility of tariff exemption even though it is spending 60 lakhs annually on electricity tariffs.
As the project is not completed, Gandaki province is suffering loss of lakhs due to not being able to benefit from the discounted electricity tariff, according to Baglung Nagarkhanepani and Consumer Organization. Hari Bahadur Gisi, Executive Chairman of Baglung Nagar Drinking Water and Consumer Organization, informed that since the builders did not complete the project and handed over the power discount agreement, they could not go to the tariff discount provided by the federal and provincial governments.
Although 95 percent of the Baglung Nagar large water supply lift project contracted on June 31, 2075 has been completed in two years, the water supply is still to be distributed through the new structure. Kankai Jayamata JV was able to build in the year 2077 and a contract was signed at a cost of 30 million 26 lakh 51 thousand . After the
, even though the cost of the project was increased by Rs. 4 crores, since the builders did not pay attention to the completion of the project, the city water supply company was forced to pay millions of electricity bills. "Gandaki province's drinking water and electricity tariff and the federal water supply have also introduced a plan to give a discount on the electricity tariff. If there was some discount on the monthly tariff of five lakh rupees, it would have been a relief," Jisi said.
Government of Gandaki Province Government of Lift Water Supply Project Electricity Tariff Subsidy Procedure, 2079 according to the project's electricity Baglung Nagar Water Supply and There is a provision that the consumer committee will get a 25 percent discount. Jisi says that the city's water supply is suffering annual losses due to construction workers not completing the work.
Jisi says that it will be a relief to get an annual discount of Rs. After the extreme crisis of water supply in Baglung market, the project is in its final stage and since May 2081, water has been drawn from two motors and distributed through an old tank near Lokmarg. The federal government has also come up with a plan to give tariff concessions in the big elevator project . Even though the builders of the
project have completed the construction, water has yet to be poured into two new seven lakh liter collection tanks above the Lokmarg and distributed to Goudakot and Rametar areas. The project to bring the water of Kathekhola located in Baglung Municipality-3 to Ratamata 250 meters above Kailampokhari has reached the final stage, but the burden of electricity tariff has fallen on the city water supply.
After the water test failed, the water pipe was changed by the Water and Sewerage Management Department. Construction businessman Krishnahari Choulagai admitted that there was a delay in the completion of the project. He said that the project site is geographically weak, there is a delay in landslide management, the corona crisis, the economic crisis and solving the pipeline design problem are the reasons for the delay in completion. The elevator project was built in such a way that the water of the Kathekhola under Baglung market was drawn and purified through the elevator and distributed.