Bridge construction in Baglung at 7 crore 66 lakhs

Baishak 27, 2082

RSS

Bridge construction in Baglung at 7 crore 66 lakhs

We use Google Cloud Translation Services. Google requires we provide the following disclaimer relating to use of this service:

This service may contain translations powered by Google. Google disclaims all warranties related to the translations, expressed or implied, including any warranties of accuracy, reliability, and any implied warranties of merchantability, fitness for a particular purpose, and noninfringement.

A motorable bridge has been constructed to connect Badigad rural municipality-7 Bhimgithe and 9 Malarani.

The construction of the bridge, which started five years ago, has been operational since last month. After the bridge became operational, the project of national pride has become easy to travel from Madhyapahari Lokmarg along with Malarani to Rajkut, Pyuthan and Gulmi.

On November 27, 2077, the road division office awarded a contract to a construction company for 76.6 million rupees. Although the contract was given to complete the construction in February 2079, the construction was completed only after three years. Bishnu Prasad Lamichhane, information officer of the road division office, informed the government that the work was not completed on time due to lack of sufficient budget.

Rajkut-Harpe-Devisthan Rolpa-Rukum-Jajarkot traffic has become easy from the newly constructed bridge Malarani.  

Local Prem Bahadur KC said that after the construction of the bridge in Badigadkhola, it became easier to market the products in the village. He said that although many farmers produce fruits and vegetables in the village, now the compulsion to carry them to the market has ended. 