77.7 percent progress on eastern section of Prithvi Highway

Falgun 8, 2081

RSS

77.7 percent progress on eastern section of Prithvi Highway

We use Google Cloud Translation Services. Google requires we provide the following disclaimer relating to use of this service:

This service may contain translations powered by Google. Google disclaims all warranties related to the translations, expressed or implied, including any warranties of accuracy, reliability, and any implied warranties of merchantability, fitness for a particular purpose, and noninfringement.

Under the Muglin-Pokhara road, the road expansion work on the eastern section of Prithvi Highway has achieved 77.7 percent physical progress.

Out of the 41.45 km road in the eastern section, 72.1 km road has been paved. Of that, 34.5 four lane and 3.1 two lane roads have been paved. According to the project, the second (final phase) of the 44 km road has been paved. Bishnu Prasad Pandey, engineer of the eastern section of the project, informed that there are 15.6 four lanes and two lanes of 12.73 km in Soma.

In the first phase, the road was paved six centimeters thick. In the second phase, the road will be paved with a total of 10 cm of 4 cm. He said that in addition to advancing the work of 'double layer' black sheeting from Markichoke of Ambukhaireni Rural Municipality of the district, the work has also been started in places where black sheeting has not been done. 

'Of the two-way road, one side of the road has been blacked out and the other side of the road has been blacked out.' China Construction Company Corporation signed a contract for Rs.

It was agreed to complete the work by May 2081. Currently, the construction work has been continued by extending the deadline again. The road is being expanded to four lanes with the loan support of Asian Development Bank ADB.