It has been almost 10 years since Dumre Customs started working on the new city project. The project, which has progressed to develop infrastructure so that one lakh population can live with essential facilities within 20 years, has shown that only one percent of economic progress has been achieved so far.
Out of the 44 billion amount included in the IDP, the project has been able to spend only 958.7 million rupees out of the budget allocation of 1.265 million rupees so far. The physical progress of the project has been 1.5 percent.
In the year 2070, a new urban development project office was established in Bhanu Municipality-1. Even after 10 years of the project, the project has not achieved the expected progress. Abhishek Adhikari, head of the project, said that the
office has spent 958.7 million rupees on various schemes from the financial year 2072/73 to the last financial year. He said, "Only one percent of the 44 billion rupees included in the IDP has been spent. As the physical infrastructure is gradually being built, the physical progress so far is minimal.
Office has been investing budget in the areas of physical infrastructure, social infrastructure, cultural and tourism, and economic infrastructure. In the financial year 2072/73, 37.4 million were allocated 23.6 million, in 2073/74 13.26 million, 88.8 million, in 2074/75 206.1 million, 192.24 million. Officials said that an expenditure of Rs.
Similarly, 40.91 million in the financial year 2075/76, 10.29 million in the financial year 2076/77, 13.49 million in the financial year 2077/78, 10.85 million in the financial year 2078/79, financial In the year 2079/80, 10 million 44 million rupees and in the financial year 2080/081, 15 million 44 million rupees have been spent.
According to the project, 958.7 million rupees have been spent out of a budget allocation of 1.265 million rupees till the last financial year. In the current financial year, 12.7 million rupees have been allocated for capital and 15.5 million rupees, according to the chief officer of the project. tell He said that no money has been spent from the allocated budget so far. Until now, through the
office, under the road network and transportation, roads have been paved, slopes, drains, sewers, gravel and unpaved roads have been constructed. 63 crore rupees have been invested in this work. Officials said that 43 kilometers of drains have been constructed for sewage management. 29 million rupees have been invested in the installation of solar lights for electricity and communication.
Green garden, Kiriyaputri building, senior citizen building, stairs, platform and toilets have been built for social infrastructure. He said that 2 million rupees have been invested in infrastructure in Siddhagufa, detailed study report of lake park and construction of stone park in terms of culture and tourism.
The office has constructed 34.78 km of road gravel, 1.24 km of slopes, 20.30 km of tarmac, 44.62 km of drains, three community buildings, one government office building, one playground, two recreational parks and one water supply scheme. It has been said.
Similarly, the office has started the process of Dumre Customs Land Consolidation Project. Officials said that 643 ropani lands have been identified for this purpose. A notification was published in the Nepal Gazette along with the details of the project on 10th January 2074. He said that the final report was submitted on December 12, 2077, and the task of designating the road fort was completed. He said, 'The acquisition of land and allocation of land has yet to be approved by the city development committee.' 1, 2, 3 and 4 Dumre Customs has started a new city project covering the former Bandipur gauis-1, 2, 3 and 4. The Acting Chief Officer said that
has been conducting programs in Palungtar for the past one year. According to him, in Palungtar Smart City, Shiv Mandir, Khoplan, Lungi, Jyotichautara, road upgrading, CCTV installation in schools have been completed and Haat Bazaar is under construction.
He said that by keeping coordination with the stakeholders and keeping the budget as a priority, it will be easier to work and the expected physical progress can also be achieved.
Similarly, the population of Bandipur rural municipality and Bhanu municipality is decreasing, he said. He said that in search of employment and basic economic prosperity, they migrated to nearby cities like Chitwan, Damauli, Pokhara, Kathmandu and other cities which are developing rapidly. According to the National Census 2068, Bandipur rural municipality had a population of 22 thousand 172, but in 2078, it has decreased to 18 thousand 532. Shivkumar Shrestha, Ward President of Bandipur Rural Municipality - 1 said that the
project has expanded the program by including Ward No. 1, 2, 3 and 4 of Bandipur Rural Municipality-1. According to him, road construction, Programs like paving, making slopes, making drains, installing solar lights, Kriyaputri building, park construction are being done.
'Until now, it does not seem to have made as much progress as should be achieved', he said, 'Allocation of the budget based on access, putting the budget where the employees want, and making plans from their own account without any coordination with the local level seems to be a problem. It would have been better to make a plan based on local economic viability and demand.
Similarly, the ward president of Bhanu Municipality-1, Kanchimaya Tamang, says that while the urban development project is working within the ward, there is no coordination with the ward president or any other concerned body. She said, "We don't know that they are working, because these works are in their own ward, they found out when they searched."