Construction of Chatra-Moolghat-Ganeshchowk road has been started under the Tamor Corridor, which was built as a fast route to connect the Himalayan districts from Terai to Hills.
The 155-kilometer long road has been paved from Wednesday in Falametar section of Dhankuta. In the first phase, from Ganeshchowk in Panchthar to Moolghat in Dhankuta, the process was started from last year to cover 112 km.
Although the government did not provide enough budget, the black paper work was not started . This year, under construction under the project, the black-paved work of the Falametar-Kushetar road section of Dhankuta has started .
The construction company Rautaha Kshamadevi JV has been entrusted with the construction of 66 km out of 112 km of Tamor Corridor . Jairam Adhikari, Engineer and Information Officer of the Tamor Corridor Project, said that in the first phase, about five kilometers of road will be paved through Phalametar-Sadamtar to Murkute-Kushetar. Jimwewari Rautah Kshamadevi JV, who blackmails
, has got it. This road has been built as a fast route to connect Eastern Nepal with India and China.
From Sunsari's Chatra through Dhankuta to Panchthar, 112 km of the 112 km road was awarded a contract for four billion 16 million rupees in October 2079. 28 km of the corridor from Moolghat to Navakhola is in the black paper stage . There is an agreement to complete the 66 km road work of Tamor Corridor in three years .
The project was started by Sarka in 2065 by allocating one million budget to connect China's Tibet through the bank of Tamor River from Jogbani in India . After that, a contract was signed for 6.15 billion 1.4 million to open a track from Mulghat in Dhankuta to Subhang in 2066 and the work started.
At present, the construction of drains on 44 kilometers of the road has been completed and the project will be able to complete the black sheet work up to Fidim within the specified time . This road is considered as the economic and strategic importance of the eastern hills. Head of Tamor Corridor Road Project Pradeep Niraula said that Rautaha Kshamadevi JV and Apex Company have signed a contract in two sections by spending 4.16 billion in Tamor Corridor.
According to the contract agreement in two packages, Rautaha Kshamadevi JV has signed a contract for 2.40 billion from Moolghat to Hangtuwa for 66 km and the remaining part has been signed by FX Company for 1.24 billion. Regular traffic is also being operated from Mulghat on the road to Panchthar and Taplejung.
The government brought this road concept to establish not only the eastern hills and the federal capital Kathmandu but also the border areas of India and China as a fast route.