Construction of 43-room building in Raksirang Rural Municipality completed

The office building has been constructed on approximately 7 acres of land at a cost of Rs. 64.2 million.

kartik 29, 2082

Pratap Bista

Construction of 43-room building in Raksirang Rural Municipality completed

We use Google Cloud Translation Services. Google requires we provide the following disclaimer relating to use of this service:

This service may contain translations powered by Google. Google disclaims all warranties related to the translations, expressed or implied, including any warranties of accuracy, reliability, and any implied warranties of merchantability, fitness for a particular purpose, and noninfringement.

The construction of the office building of the remote Raksirang Rural Municipality in the district has been completed. A four-story, 43-room building has been constructed in Chainpur, the center of the rural municipality.

Construction work began in Ashar 2078. According to the agreement, the construction work should have been completed by mid-Ashar 2082. Chairman Rajkumar Malla said that the construction work of the municipality building has been completed even though it was 4 months behind schedule. 'Now, the construction company will hand over the building to the municipality within two weeks,' he said.

Jayamata Engineering Construction Company had taken the contract for the construction work. The construction company is currently in the process of handing over the building,' said Dharmaraj Chaudhary, a technician at the municipality. The office building was built on about 7 acres of land at a cost of Rs 64.2 million. After the building is handed over, all the offices and branches of the municipality will be under one roof, said Malla, the chairman of the municipality.

The office of Raksirang Rural Municipality is currently in Chainpur. Ekna has been providing services to the residents of the municipality by constructing adobe buildings. The branches of health, agriculture and other organizations are taking shelter in the buildings of other organizations. Among the 10 municipalities in Makawanpur, the administrative buildings of Manahari, Indrasarobar and Bakaiya rural municipalities are under construction. Bhimphedi, Kailash and Makawanpurgadhi have already constructed their municipal buildings. Bagmati rural municipality, located in the far east of the district, will construct a concrete building for the municipal office in the current fiscal year, said Sarkes Ghalan, the municipality's chairman. Bagmati rural municipality is providing services to the residents of the municipality by constructing a kutta building in Jhurjhure. Hetauda Sub-metropolitan City and Thaha Municipality have their own concrete and well-equipped buildings. The main administrative building of Hetauda Sub-metropolitan City was set on fire and vandalized during the Genji movement. The building is currently being renovated.