The construction of the bridge has been incomplete for five years

The under-construction motorable concrete bridge over the Brahmayani River has been stalled for five years.

Bhadra 8, 2082

RSS

The construction of the bridge has been incomplete for five years

We use Google Cloud Translation Services. Google requires we provide the following disclaimer relating to use of this service:

This service may contain translations powered by Google. Google disclaims all warranties related to the translations, expressed or implied, including any warranties of accuracy, reliability, and any implied warranties of merchantability, fitness for a particular purpose, and noninfringement.

Motorable concrete bridge under construction on Brahmayani River in Jugal Rural Municipality of Sindhupalchok has been stuck for five years. Surya JV Construction Company was entrusted to build the bridge at a cost of eight crores to complete the construction in two years.

On 23rd Chait 23rd of 2078, the then Speaker Agni Prasad Sapkota laid the foundation stone of the 63 meter long bridge connecting Jugal Rural Municipality-1 and 5. According to Himal Shrestha, the vice president of Jugal rural municipality, the local government has repeatedly requested to proceed with the construction work, but the businessmen involved in the construction are ignoring it.

According to him, the residents of Selang and Golche gauis in Sawik will benefit after the bridge is built. Vice President Shrestha says that the main contractor has entrusted the construction work to the subcontractor and the contractor is losing contact.  Ganesh Archay, the proprietor of Surya JV Construction Company, which has been entrusted with the construction of

, says that although the drawing design has been 'approved', the work has not started because the Charikot division office has not made the VO. "We wanted to do the bridge immediately. But it was difficult to work because the road division office Charikot did not pay the VO", he said.

He claims that the road division office Charikot has not paid the bill for two years. The middle pillar of the bridge is 10 inches different and the drawing of the bridge has been rebuilt and approved, so the work of VO and bill payment will not be stopped, says Akash Shrestha, division head of the road division office Charikot.

Jugal rural municipality-5 ward president Ravindra Ghimire says that the people have to suffer because the bridge is dilapidated